1⟩ What are the common PM interview questions?

1)What about class & characteristics is it also the same

thing

2)counter is triggers order when particular value set

comes ,so is it possible to trigger it on alpha bet instead

of digit reference for any type of counting . i.e. Is it

possible to count alpha bet instead of digit?

3) When I search that t code on sap forum It will show for

sub order .So when & why we create sub order

4) What is significance of T code iw36.

5) In IMG settings, Maintain the Value category for

Internal labor cost, and assigned to appreciate cost

elements group.

 124 views

2⟩ What is the use of item number in maintenance order?

Item number refers to the number (not material number) to

identify the material component that is to be used for an

operation in the maintenance order.It is generally given in

increments of 0010.It is the first field in the Components

tab of a maintenance order.

 124 views

3⟩ What is refurbishment order? Explain the total cycle?

Refurbishment order is used for upgradation of damaged /

defective spare parts and are sagregated as condition

based . eg C1, C2 and C3

CYCLE:

create refurbishment order- withdrawawal of spare parts

from store- refurbishment execution- order completion

confirmation- refurbished parts back to store- goods

receipt for returning

 128 views

5⟩ How to set the deletion flag to Functional location and also want to know how to hide the flagged Functional location?

You can use transaction code IL02 to change functional

location, highlight the respecitve functional location and

go to edit at the top tool bar, their you select functions

change and their you can click delete, to set a flag delete.

You cannot hide this fucntional location when you display

IH01 , the functional location heirarchy is displayed but

once you click it , the screen appears showing the

functional location is created with flag for deletion

 134 views

6⟩ How to schedule counter base maintenance plant for DG in power plant that need 800hr per month maint this steps i followed.1)i have created meas pt with counter (IK01) created meas document IK11 then schedule thru IP10.but not getting due order list in ip24

First of all, you cannot get 800 hrs per month...

For counter based... it will schedule in two days... like..

days and hours... but.. if u schedule in IP10..it wil take

the annual reading and schedule the dates.. So.. if the

running hrs didn't reach, but the date reached... so.. it

will open a order...

Give the annual reading according to the running hrs of the

DG.. then u will get

 144 views

7⟩ What is Work Centre Categoey?

Basically work center category decides the capacity (means

ability to do work). The category defines the activity type

for costing and scheduling the categories mainly we come

accross in the production are labour and machine. Hence to

define labour cost, machine cost and setup cost we define

work center category to create work center and we enter

defaults therein. For a period of time if there are no much

changes we generally prefer production line, and if there

are much changes in the production we prefer activity type

for individual order which we call production order. By

this you can understand cat type 001 for machine and cat

type for labour.

Work center category used to define which screen selection

& field selection for a particular work center.

 128 views

8⟩ What is aMilestone Confirmation?

The milestone confirmation is a special form of

confirmation, in which the confirmation of one operation

causes other operations or suboperations to be

automatically confirmed at the same time.

Milestones are operations that have the corresponding

indicator in the control key.

Operations can be defined as milestone operations in their

control keys. If a milestone operation is confirmed, then

previous operations are automatically confirmed.

 139 views