Answers

Question and Answer:

  Home  Construction Manager

⟩ Pick up incorrect statement from following A. The activity is the time consuming part of a project B. The beginning and end of a job, are called events C. The activity which consumes maximum time, is called a node D. Logically and sequentially connected activities and events form a network E. None of these

C. The activity which consumes maximum time, is called a node

 156 views

More Questions for you: