⟩ Suppose if D is the duration, ES and EF are the earliest start and finish, LS and LF are latest start and latest finish time, then the following relation holds good A. EF = ES + D B. LS = LF - D C. LF = LS + D D. D = EF - ES E. all the above.

E. all the above.