Answers

Question and Answer:

  Home  Cost Management

⟩ A schedule performance index (SPI) of 0.76 means A. You are over budget B. You are ahead of schedule C. You are only progressing at 76 percent of the rate originally planned D. You are only progressing at 24 percent of the rate originally planned

C. You are only progressing at 76 percent of the rate originally planned

 164 views

More Questions for you: