⟩ A schedule performance index (SPI) of 0.76 means A. You are over budget B. You are ahead of schedule C. You are only progressing at 76 percent of the rate originally planned D. You are only progressing at 24 percent of the rate originally planned
C. You are only progressing at 76 percent of the rate originally planned