Answers

Question and Answer:

  Home  Cost Management

⟩ You have been asked to select between three projects. Project A has a net present value of $54,750 and will take six months to complete. Project B has a net present value of $85,100 and will take two years to complete. Project C has a net present value or $15,000 and a benefit-cost ratio of 52. Which project should you choose? A. Project A B. Project B C. Project C D. There is not enough information to decide.

B. Project B

 165 views