Answers

Question and Answer:

  Home  Cost Management

⟩ You've been hired by a large consulting firm to evaluate a software project for them. You have access to the CPI and EV for the project, but not the AC. The CPI is .92 and the EV is $172,500. How much money has actually been spent for the project? A. $158,700 B. $172,500 C. $187,500 D. There is not enough information to calculate the actual cost.

C. $187,500

 173 views

More Questions for you: