⟩ The cost contingency reserve should be A. Hidden to prevent management from disallowing the reserve B. Added to each activity to provide the customer with a shorter critical path C. Maintained by management to cover cost overruns D. Added to the base costs of the project to account for risks
D. Added to the base costs of the project to account for risks