A construction schedule is prepared after collecting A. number of operations B. output of labor C. output of machinery D. quantity of various items E. all the above
CPM is A. synthesizing in concepts B. is built of activities oriented program C. is based on time estimate D. is used for repetitive works E. all the above
Construction team means A. an engineer B. an architect C. an owner D. a contractor E. all the above
Critical path lies along the activities having total float A. positive B. negative C. zero D. same
The performance of a specific task in CPM, is known A. Dummy B. Event C. Activity D. Contract
Final technical authority of a project lies with A. Assistant Engineer B. Executive Engineer C. Superintending Engineer D. Chief Engineer
Bar charts are suitable for A. minor works B. major works C. large projects D. all the Above