⟩ Why to have regular team meetings?
Communication is crucial to the success of your team. Meetings keep everyone up-to-date on the status of projects and any changes that may need to be implemented.
Communication is crucial to the success of your team. Meetings keep everyone up-to-date on the status of projects and any changes that may need to be implemented.
A Milestone chart A. shows the inter-dependencies of various jobs B. depicts the delay of jobs, if any C. points outgoing ahead of schedule of jobs, if any D. none of these.
A lock-box service is used for A. depositing cash when bank is closed B. paying bank customer bills automatically C. storing papers in a bank vault D. depositing payments to bank customers E. None of the above
Inventory is also referred to as A. stock B. warehouse capacity C. materials D. materials in hand E. None of the above
Controls of data communication deal with A. the communication channel B. the computer C. terminals D. All of the above E. None of the above
Pick up the correct statement from the following A. The float may be positive, zero or negative B. If the float is positive and the activity is delayed by a period equal to its total float, the completion of project is not delayed C. If the float of an activity is negative, delay in its performance is bound to delay the completion of project D. If the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project E. All the above.
The difference between the time avail-to do a job and the time required to do the job, is known as A. event B. float C. duration D. constraint
The operations file is updated by the A. production control system B. MRP system C. shipping system D. All of the above E. None of the above
Time and progress chart of a construction, is also known as A. Bar chart B. Gantt chart C. Modified Mile stone chart D. Critical path method chart E. All the above
Which one of the following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast E. all the above
The technique for establishing and maintaining priorities among the various jobs of a project, is known A. Event flow scheduling technique B. Critical ratio scheduling C. Slotting technique for scheduling D. Short interval scheduling