Answers

Question and Answer:

  Home  Management

⟩ Critical Path Net Work helps an engineer A. to concentrate his attention on critical activities B. to divert the resources from non-critical advanced activities to critical activities C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project D. all the above

D. all the above

 204 views

More Questions for you: