⟩ How do you estimate in the three point estimating method?

One optimistic estimate, a pessimistic estimate and one most likely estimate is considered for an activity. (Op estimate+6 X most likely+ pess. Estimate) is calculated and divided by 6. This result then may be further iterated. This is the estimate to be used."0"