⟩ When the Internal Requisition will get generate if I define an OSP operation in sequence 30. 10 & 20 will be other than OSP operations?

The purchase requisition (PR) gets generated for OSP and not

the internal requisition.

And it depends on the Requisition Creation Time

parameter in WIP Parameters 'Outside Processing' Tab.

1. At Job/Schedule Release - The PR gets generated

immediately after the Job or Schedule is released.

2. At Operation - The PR gets generated once the move

transaction reach the Queue of the OSP operation sequence.

3. Manual - PR need to be generated manually.