⟩ Measurement has revealed the following information on an operations system. Design capacity was 84 units per hour, planned losses were 12 units per hour, and actual output was 65 units per hour. What were the utilization and efficiency of the operation respectively?

1. 77% & 90%

2. 78% & 90%

3. 54% & 92%

4. 68% & 83%

5. 77% & 84%

77% & 90%