⟩ Explain ETVX concept?
E- Entry Criteria
T- Task
V- Validation
X- Exit Criteria
ENTRY CRITERIA: Input with 'condition' attached.
e.g. Approved SRS document is the entry criteria for the design phase.
TASK: Procedures.
e.g. Preparation of HLD, LLD etc.
VALIDATION: Building quality & Verification activities
e.g. Technical reviews
EXIT CRITERIA: Output with 'condition' attached.
e.g Approved design document
It is important to follow ETVX concept for all phases in SDLC.