Job seeker should mention a time where he/she had to use reason and logic to resolve a problem. Job seeker may have analyzed all the relevant information and created a good, effective solution.
Job seeker should mention a time where he/she had to use reason and logic to resolve a problem. Job seeker may have analyzed all the relevant information and created a good, effective solution.
Overall in-charge of an organisation at the site responsible for the execution of the works, is A. Executive Engineer B. Engineer C. Junior Engineer D. Sub overseer E. Assistant Engineer
First method invented for planning projects, was A. Bar chart method B. Milestone chart C. Critical path method (CPM) D. Program Evaluation and Review Technique (PERT)
Works costing less than Rs. 20,000 and are treated as A. projects B. major projects C. minor projects D. all the above
Bar charts are suitables for A. minor works B. major works C. large projects D. all the Above
Estimated time required to perform an activity, is known as A. event B. dummy C. duration D. float
If total float and duration of an activity are 5 and 10 days respectively, the particular activity can be A. started 5 days later B. completed 5 days later C. performed at slower rate in 15 days D. all the above
The Modular co-ordination of construction means proper A. planning B. designing C. execution D. all the above
Which one of following represents an activity A. excavation for foundation B. curing of concrete C. setting of question paper D. preparation of breakfast E. all the above
Time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as A. duration B. total flat C. free float D. interfering float
Artificial activity which indicates that an activity following it, cannot be started unless the preceding activity is complete, is known as A. event B. free float C. dummy D. constant