Answers

Question and Answer:

  Home  PMI Certification

⟩ One a project, quality should generally be of A. Equal priority with schedule, but higher priority than cost. B. Higher priority than cost and schedule. C. Equal priority with cost, but higher priority than schedule. D. Equal priority with cost and schedule.

D. Equal priority with cost and schedule.

 225 views

More Questions for you: