⟩ You are the project manager for a railroad construction project. Your Sponsor has asked you for a forecast for the cost of project completion. The project has a total budget of $80,000 abd CPI of .95 . The project has spent $25,000 of its budget so far. How much more money do you plan to spend on the project? A. $59,210 B. $80,000 C $84,210 D $109,210
A. $59,210