⟩ Explain The PERT method is MOST used in situations where A. It is important to know the interrelationships of activities. B. Little is known about the cost estimated related to the project. C. Little experience exists on which to base estimated of activity duration. D. Resource requirements are well defined.
C. Little experience exists on which to base estimated of activity duration.