⟩ Can you explain what other advice would you give to a job seeker looking to gain employment?
Be clear about what job you’re applying for.
Be clear about what job you’re applying for.
What experience do you have as Contract Manager?
Do you know about our company?
Describe a typical work week for contracts manager position?
Which of the following is NOT needed in order to come up with a project estimate? A. A WBS B. A network diagram C. Risks D. A change control system
A schedule performance index (SPI) of 0.76 means A. You are over budget B. You are ahead of schedule C. You are only progressing at 76 percent of the rate originally planned D. You are only progressing at 24 percent of the rate originally planned
A cost performance index (CPI) of 0.89 means A. At this time, we expect the total project to cost 89 percent more than planned B. When the project is completed we will have spent 89 percent more than planned C. The project is only progressing at 89 percent of the rate planned D. The project is only getting 89 cents out of every dollar invested
Who has the cost risk in a fixed price (FP) contract? A. The team B. The buyer C. The seller D. Management
The main focus of life cycle costing is to A. Estimate installation costs B. Estimate the cost of operations and maintenance C. Consider installation costs when planning the project costs D. Consider operations and maintenance costs in making project decisions
Cost performance measurement is BEST done through which of the following? A. Asking for a percent complete from each team member and reporting that in the monthly progress report B. Calculating earned value and using the indexes and other calculations to report past performance and forecast future performance C. Using the 50/50 rule and making sure the life cyde cost is less than the project cost D. Focusing on the amount expended last month and what will be expended the following month
Estimate at completion (EAC) is a periodic evaluation of A. The cost of work completed B. The value of work performed C. The anticipated total cost at project completion D. What it will cost to finish the job